Copperline Distribution Center
- Sector
- Industrial & distribution
- Region
- Fairhaven metro
- Building area
- 1,100,000 sf
- Year
- 2024
- Status
- Complete
Self-performed on this job
White — proposed excavation- Mass earthwork
- Site utilities
- Slab on grade
Everything above was built by our own crews and equipment. When the ground turned up something the drawings did not show, the superintendent redirected them that morning.
What was hard
The tenant's lease started fourteen months from notice to proceed, and the geotechnical report came back with two feet of undocumented fill across the eastern half of the site. Removing it the conventional way would have taken the schedule.
What we did
Our own earthwork crews mobilized the week of award and balanced the cut and fill on site rather than hauling, while the slab and dock package was released early against a model that was already clash-free. The building was dried in before the fill work on the east half was finished.
What it produced
Beneficial occupancy on the lease date, with no export trucking on the public road at any point.
On this project
- Building area
- 1,100,000 sf
- Delivery
- CM at Risk
- Dock doors
- 196
- Self-performed
- Dirt, utilities, slab
Scope
- Preconstruction and GMP
- Mass earthwork
- Site utilities
- Slab on grade
- Tilt-up erection and structural steel
- Dock equipment and truck court
- Fire protection and MEP coordination