Ironwood Manufacturing
- Sector
- Industrial & distribution
- Region
- Marrow Valley
- Building area
- 320,000 sf
- Year
- 2023
- Status
- Complete
Self-performed on this job
White — proposed excavation- Mass earthwork
- Equipment foundations
- Slab on grade
Everything above was built by our own crews and equipment. When the ground turned up something the drawings did not show, the superintendent redirected them that morning.
What was hard
Process equipment foundations were still being engineered while the shell had to come out of the ground, and the equipment vendor's loads changed twice during construction.
What we did
We sequenced the shell independently of the process areas and left the equipment pads as a late, self-performed concrete package our own crews could turn quickly when the final loads landed.
What it produced
Two vendor load changes absorbed without a schedule extension, because the concrete crew was ours to redirect.
On this project
- Building area
- 320,000 sf
- Delivery
- CM at Risk
- Equipment pads
- 22
- Load revisions
- 2, absorbed
Scope
- Preconstruction and GMP
- Mass earthwork
- Process and equipment foundations
- Structural steel and metal panel
- Heavy MEP coordination
- Commissioning support